Mon, Oct

Completion of 48 Development Projects in one Month

Reconstruction
Typography

The 48 sub projects completed in various villages of the provincial capital, Burka, Nahrin, Dushi, Dahne Ghori, Deh Salah, Tala wa Barfak and Pul-I-Hisar districts of Baghlan province will enable approximately 8,184 households to have access to better services .


road constructionThese projects encompass the construction of water supply network 27243 meters in length, gravelling of rural roads 20-km in length, four schools, retaining wall 2477-m in length, a bridge, 47 culverts, excavation of 40 semi-deep water wells, 12 water reservoirs and two micro hydro power plants.
These projects have been completed and handed-over in the month of Saratan through the National Solidarity Program of the Ministry of Rural Rehabilitation and Development (MRRD/NSP) at a budget of AFN 74 million and 355 thousand.